CN41N Report Actual cost added to Actual Revenue




Hierarchy reports like CN41 , CN41N , is not either showing actual revenue or Actual revenue is added to Actual cost and the value is displayed as negative.

This is due to wrong configuration of value category. Different value categories should be created for cost and revenue so that the hierarchy report can segregate cost from revenue.

Reference Transaction Code

CJVC : Analyze value category assignment

CJEN : Reconstruct Project Info DB

 

 

 

Note ; Execute CJEN to reconstruct the project after configuration changes

 




Reference

Reference Links